Twelve Network Checks UK Operations Teams Should Make Before an Office Move
Moving office is a property project until the first Monday morning, when it becomes a network project. Staff arrive, laptops open, the coffee machine starts, and the organisation discovers that the broadband circuit is still in survey, the comms room key is with the landlord, or the main number has not ported. The good news is that most of these problems are predictable. They are also avoidable with a checklist and a named owner.
Why the network needs its own runbook
Most relocation plans have workstreams for furniture, signage, security and cleaning. The network often sits in a spreadsheet cell marked IT. That is understandable, but it is also how organisations end up with staff sitting on boxes while a fibre circuit waits for a wayleave. The following twelve checks are not exotic. They are the basics that busy operations teams forget because the move itself consumes attention.
1. Start broadband and circuit orders early
Leased lines and business fibre can take 30 to 90 days, sometimes longer if a wayleave, building works or landlord consent is needed. Order as soon as you have the address and permission to install. Ask for the actual lead time in writing, not the sales estimate, and build a contingency into the move plan.
2. Confirm comms room access and space
Find out where the comms room is, who holds the keys, and whether your rack will fit. Check power, cooling, security and access hours. If the building has a shared riser or a locked cabinet, confirm that your equipment can be installed and serviced without a site-wide escort every time.
3. Treat structured cabling as a project, not an afterthought
Cat6 or Cat6a cabling, patch panels, labelling and certification should be specified before fit-out. Do not assume existing cabling is fit for purpose just because it is present. A certified cabling installer will test and document the installation, which saves time when something fails later.
4. Time the Wi-Fi survey correctly
A Wi-Fi survey is most useful after fit-out and before occupancy. Walls, glass, racking, furniture and neighbouring networks all affect coverage. Survey too early and the design may not match reality; survey too late and you may be moving access points after the ceilings are closed.
5. Plan VoIP number porting
Number porting has lead times and paperwork. Give the provider the correct account numbers, addresses and authority letters. Avoid porting on a Friday afternoon, and keep a fallback route for incoming calls during the cutover. If you use a hosted phone system, confirm that the new site has sufficient bandwidth and power protection.
6. Surface landlord constraints early
Wayleaves, listed buildings, alterations, riser access, working hours and insurance requirements can all delay a network installation. Get permissions in writing. If the landlord controls the comms room or roof access, confirm the process for engineers and the notice required for visits.
7. Check circuit diversity and resilience
One fibre into the building is a single point of failure. Consider whether a second path is practical, and plan a 4G or 5G backup for essential services. Resilience does not have to mean duplication of everything, but it should mean a tested plan for the connections that keep the business trading.
8. Confirm power and UPS in the comms room
Switches, routers and phone systems need clean, protected power. Confirm the number of sockets, the UPS runtime and whether the comms room has its own circuit. A short power cut should not take down the network if a modest UPS can prevent it.
9. Label and document the patching
Patch schedules, port maps and cabinet elevations are dull until the day something fails. Ask the installer to provide documentation and labels that match the actual installation. Future you, or the next IT provider, will be grateful.
10. Agree an out-of-hours cutover and rollback plan
Cutover on a weekend or evening where possible. Name a decision-maker, agree a rollback point and test the new connection before the old one is ceased. The aim is not heroics; it is a controlled change with a way back if something unexpected happens.
11. Do not forget physical security
Door access, CCTV, alarms and locked cabinets matter. Network security starts with the room. If the comms room is shared, confirm who else has access and how changes are recorded.
12. Decommission the old site properly
Cease old circuits, recover equipment, wipe data and return landlord equipment. Keep records of what was returned and when. A forgotten circuit can keep billing for months after the move, and a forgotten switch can become a data protection problem.
A calm cutover is a planned cutover
None of these checks requires a large IT team. They require a checklist, an owner and a realistic timetable. At Synetrix, the advice is simple: give the network its own workstream in the move plan, with deadlines that sit before the furniture arrives. The goal is not a perfect move. It is a move where the surprises are small, the phones work, and staff can get on with the job.